Backflow testing
Initial and annual tests of every testable assembly, with the report filed with your municipality.
What happens during a testWe test backflow preventers, survey cross-connections, repair failed assemblies and file the reports with your municipality. We also do commercial plumbing.


Initial and annual tests of every testable assembly, with the report filed with your municipality.
What happens during a test
A walkthrough of the property's water uses and connections, and a report on what protection is missing. Our survey does not interrupt the water supply.
How a survey differs from a test
If a device fails, we find the cause, send a repair scope for approval and retest the assembly after the work.
Field note: a relief valve failure
RPZ, double check and vacuum breaker assemblies, chosen for the hazard and sized for the building's water demand. We install Zurn Wilkins, Watts and Apollo assemblies. We prepare the permit drawings, arrange sealed drawings where the municipality requires them, book the inspections and file the first test. There is no charge for a site visit to quote.
Field note: a DCVA on a vertical riser
Test records, survey documents and municipal submissions, plus a courtesy reminder before your next test date; the due date remains the owner's responsibility.

Underground and overhead rough-in, bar and restaurant plumbing, and general commercial plumbing for commercial, institutional and multi-residential properties.
Field note: plumbing a warehouse unitOne device list, one schedule and one set of records across your properties.
We also maintain boilers and rooftop units for buildings where we look after the backflow devices. Heating and cooling
The degree of hazard sets the type of assembly. A survey or your municipality classifies the hazard. Read the device guide
| Assembly | Protects against | Typical use |
|---|---|---|
| RPZReduced-pressure assembly, also called an RP | Backpressure and backsiphonage, including high hazards | Premise isolation where chemicals or contaminants are present: food processing, medical and dental, industrial |
| DCVADouble check valve assembly | Backpressure and backsiphonage, lower hazards | Premise isolation for many commercial and multi-residential buildings |
| DCDA / RPDADetector assemblies | Same as DCVA or RP, with a meter bypass that detects flow | Fire sprinkler services |
| PVBPressure vacuum breaker | Backsiphonage | Irrigation connections |
Every program has its own by-law, forms and deadlines. Start with the municipality that sent your notice.
Not sure what your notice asks for? Read what a backflow notice requires.
Each page has that municipality's rules, permit and fees. Municipalities without a page link to their section of the regional guide.
| Municipality | Program and by-law | Test report due (days after the test) | Spec-Mark Group |
|---|---|---|---|
| City of Toronto | |||
| Toronto | City of Toronto, Municipal Code Chapter 851 | 7 days | Certified testers; reports filed through the City's online system |
| Scarborough | City of Toronto, Municipal Code Chapter 851 | 7 days | Certified testers; office in Scarborough |
| Region of Peel | |||
| Mississauga | Region of Peel, By-law 10-2017 | 14 days | On Peel's qualified contractor list (May 2026) |
| Brampton | Region of Peel, By-law 10-2017 | 14 days | On Peel's qualified contractor list (May 2026) |
| Caledon | Region of Peel, By-law 10-2017 | 14 days | On Peel's qualified contractor list (May 2026) |
| Halton Region | |||
| Oakville | Halton Region, By-law 71-19 | 28 days | Send us the notice; we confirm the next step |
| Burlington | Halton Region, By-law 71-19 | 28 days | Send us the notice; we confirm the next step |
| Milton | Halton Region, By-law 71-19 | 28 days | Send us the notice; we confirm the next step |
| Halton Hills | Halton Region, By-law 71-19 | 28 days | Send us the notice; we confirm the next step |
| York Region | |||
| Markham | City of Markham, By-law 2012-27 | 14 days | On the City's list of qualified persons, as Spec-Mark Mechanical (March 2026) |
| Richmond Hill | City of Richmond Hill, By-law 125-14 | 14 days | Send us the notice; we confirm the next step |
| Vaughan | City of Vaughan, By-law 177-2020 | 14 days | On the City's Approved Qualified Company List, all functions (October 2026) |
| Aurora | Town of Aurora, By-law 6213-19 | 15 days | On the Town's Approved Qualified Company List, all functions (August 2026) |
| Region of Durham | |||
| Oshawa | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| Pickering | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| Whitby | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| Ajax | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| Clarington | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| Uxbridge | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| Scugog | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| Brock | Region of Durham, By-law 24-2018 | 28 days | On Durham's qualified contractor list, as Spec-Mark Mechanical |
| City of Hamilton | |||
| Hamilton | City of Hamilton, By-law 10-103 | 14 days | Send us the notice; we confirm the next step |
A cross-connection survey looks at the whole property to find where drinking water could be contaminated and what protection is needed. A test checks that an installed backflow assembly is working.
It depends on the program. In Toronto, a survey is updated every five years, and sooner if the hazard on the property increases.
Yes. We test testable assemblies regardless of who installed them, and file the report with your municipality.
Most houses are outside the GTA programs. Peel includes single homes over 600 m². Markham includes houses with an auxiliary water supply, a lawn sprinkler system, or a fire protection system other than a full flow-through sprinkler system. Halton requires a device on every lawn irrigation system. In Peel and Markham those owners must comply as well, and we take that work. We do not take general house plumbing.
The property address, the municipality, how many devices are on site, any notice or deadline, and a contact for access on the day. For a failed device, also send the failed test report, photos of the device and its tag, and any repair history.